Create an Effectiveness Check

Who can complete this task? Veeva Quality Basics: Change Control Owner

Effectiveness checks allow the assigned Owner to document whether the change implementation was effective or ineffective, or if the results of the change are inconclusive. Effectiveness Checks are completed after the Change Control is closed.

To create an effectiveness check for a change control:

  1. Open the Complete Change Plan task for the change control.

    Screenshot step 1

  2. Open the Effectiveness Checks section and click Create.

    Screenshot step 2

  3. Fill in the required information, including a description of the activities required to check for effectiveness of the executed plan, and click Save.

    Screenshot step 3

  4. Click Manage Team.

    Screenshot step 4

  5. Select an effectiveness check Owner and QA Approver(s) and click Save.