Create an Impact Assessment

Who can complete this task? Veeva Quality Basics: Change Control Owner

Impact assessments allow the assigned Owner to document potential impacts that may occur when implementing the change plan. Impact Assessments are completed during the change planning process.

To create a change control impact assessment:

  1. Open the Complete Change Plan task for the change control.

    Screenshot step 1

  2. Open the Impact Assessments section and click Create.

    Screenshot step 2

  3. Fill in the required information and click Save.

    Screenshot step 3

  4. Click Manage Team.

    Screenshot step 4

  5. Select an impact assessment Owner and click Save.